Use the market evidence to sharpen a commitment checklist—not to replace site diligence.
| Decision | Minimum evidence this desk recommends requesting |
|---|---|
| Extend a land option | Parcel-specific service correspondence; planning status; dependencies; expiry dates; next non-refundable payment |
| Fund utility works | Executed service terms; study scope; network works; target-date conditions; collateral and cancellation exposure |
| Reserve colocation | Phase-specific critical IT MW; technical configuration; acceptance criteria; billing start; delay remedies |
| Release GPU orders | Integrated facility, cooling, network, installation and acceptance sequence with named owners |
| Approve financing | Contracted versus operational capacity; remaining cost to complete; tenant support; slower-ramp and delay sensitivities |
For each capacity claim, record: what it measures, its source date, its conditions, who confirms it and what must happen next. Use separate statuses such as document-supported, conditional, conflicting and not established.
Sources & research context
Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.