Market data and deal flow · 2026-10-16

What evidence should precede the next land, utility or hardware commitment?

Use the market evidence to sharpen a commitment checklist—not to replace site diligence.

Decision Minimum evidence this desk recommends requesting
Extend a land option Parcel-specific service correspondence; planning status; dependencies; expiry dates; next non-refundable payment
Fund utility works Executed service terms; study scope; network works; target-date conditions; collateral and cancellation exposure
Reserve colocation Phase-specific critical IT MW; technical configuration; acceptance criteria; billing start; delay remedies
Release GPU orders Integrated facility, cooling, network, installation and acceptance sequence with named owners
Approve financing Contracted versus operational capacity; remaining cost to complete; tenant support; slower-ramp and delay sensitivities

For each capacity claim, record: what it measures, its source date, its conditions, who confirms it and what must happen next. Use separate statuses such as document-supported, conditional, conflicting and not established.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.