Market data and deal flow · 2026-10-16

What should buyers take from the market now?

The evidence supports strong infrastructure demand, but not the assumption that announced capacity is available capacity. CBRE reports that primary-market supply increased 33.7% year on year in H1 2026 while vacancy stood at 1.4%. For a buyer, the important question remains whether a particular block meets its technical requirements and activation date. (cbre.com)

Three recent developments sharpen that distinction:

  • Contracts are filtering speculative power requests. AEP Ohio’s February 2026 update separates initial enquiries, paid studies and binding service contracts rather than treating them as equivalent demand. (aepohio.com)
  • Lease value and delivery risk can rise together. Cipher’s September 2026 Barber Lake amendment increased contracted revenue while revising delivery phasing and allocating additional construction costs. (globenewswire.com)
  • Actual delivery deserves its own category. Applied Digital announced additional ready-for-service capacity in October 2026 at a campus that was already fully leased. Delivery therefore did not create an equivalent amount of open-market availability. (ir.applieddigital.com)

Desk recommendation: organise market intelligence around three separate records: capacity and delivery evidence; recurring and upfront costs; and transaction status. Do not combine them into a single market-growth score.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.

  1. www.cbre.com
  2. www.aepohio.com
  3. www.globenewswire.com
  4. ir.applieddigital.com
Read the complete report and source register →

Put the evidence to work.

Keep your requirements, open questions and commitment conditions together.