Keep facility construction and tenant technology expenditure separate. JLL’s 5 January 2026 outlook forecasts a global average construction cost of $11.3m/MW in 2026, up from $10.7m/MW in 2025, and describes its chart’s scope as shell and core. It separately notes that AI technology fit-out can cost as much as $25m/MW. These are global benchmarks, not US site-specific bids. (jll.com)
As a clearly labelled screening calculation, applying $11.3m/MW to a hypothetical 50 MW project produces $565m. That is an order-of-magnitude reference, not a complete development budget. Do not add the fit-out upper figure automatically: the actual technical scope must first be reconciled.
A construction comparison should ask each estimator to identify whether its number includes:
| Cost category | Question to resolve before comparison |
|---|---|
| Land and development | Acquisition, site preparation, professional fees and permitting included? |
| Grid connection | Utility contributions, off-site works and substation scope included? |
| Electrical infrastructure | Resilience configuration and equipment procurement basis aligned? |
| Cooling | Heat rejection, distribution, CDUs and residual air cooling assigned to which party? |
| Tenant infrastructure | Networking, racks, servers and installation included or excluded? |
| Delivery risk | Contingency, escalation, financing and commissioning treated consistently? |
The checklist is this desk’s recommended budget-reconciliation method. Public benchmarks do not establish a universal liquid-cooling retrofit cost or a universal US cost per commissioned AI MW.