Market data and deal flow · 2026-10-16

What should developers budget for construction and AI fit-out?

Keep facility construction and tenant technology expenditure separate. JLL’s 5 January 2026 outlook forecasts a global average construction cost of $11.3m/MW in 2026, up from $10.7m/MW in 2025, and describes its chart’s scope as shell and core. It separately notes that AI technology fit-out can cost as much as $25m/MW. These are global benchmarks, not US site-specific bids. (jll.com)

As a clearly labelled screening calculation, applying $11.3m/MW to a hypothetical 50 MW project produces $565m. That is an order-of-magnitude reference, not a complete development budget. Do not add the fit-out upper figure automatically: the actual technical scope must first be reconciled.

A construction comparison should ask each estimator to identify whether its number includes:

Cost category Question to resolve before comparison
Land and development Acquisition, site preparation, professional fees and permitting included?
Grid connection Utility contributions, off-site works and substation scope included?
Electrical infrastructure Resilience configuration and equipment procurement basis aligned?
Cooling Heat rejection, distribution, CDUs and residual air cooling assigned to which party?
Tenant infrastructure Networking, racks, servers and installation included or excluded?
Delivery risk Contingency, escalation, financing and commissioning treated consistently?

The checklist is this desk’s recommended budget-reconciliation method. Public benchmarks do not establish a universal liquid-cooling retrofit cost or a universal US cost per commissioned AI MW.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.