Market data and deal flow · 2026-10-16

Where is capacity tight—and what does that mean for a shortlist?

Regional data is useful for prioritising enquiries, not proving that a particular site can receive power. The following observations are deliberately narrower than a “best states for data centres” ranking.

Market Dated evidence Recommended buyer response
Northern Virginia CBRE’s H1 2026 chapter says capacity delivering during 2026 was committed and that contiguous 5–10 MW requirements were difficult to accommodate. Published with the 27 August 2026 report. (cbre.com) Require a named building, phase and contractual availability date. Revalidate any offer described simply as available in Northern Virginia.
Dallas–Fort Worth 95% of more than 765 MW under construction was preleased; an additional 3.7 GW was planned but not under construction, H1 2026. (cbre.com) Separate leased construction from speculative greenfield potential. A search for “10 MW AI colocation capacity available Dallas” needs building-level evidence.
Atlanta CBRE reports turnkey facilities preleasing approximately 12 months before completion and build-to-suit projects approximately 2.5 years ahead, H1 2026. (cbre.com) Compare contractual reservations and delivery conditions, not just the size of the construction pipeline.
Silicon Valley 509.2 MW inventory, 4.2% vacancy and 144 MW under construction, H1 2026; release dated 1 September 2026. (cbre.com) Do not infer that the reported vacancy forms one contiguous, high-density deployment block. Request configuration and cooling evidence.

These recommendations are analyst interpretations, not assertions that suitable inventory is impossible to obtain.

How much of a utility enquiry pipeline becomes a binding commitment?

AEP Ohio provides a useful disclosed example. Its 13 February 2026 update reported the following progression for the requests being filtered through its new data-centre process. (aepohio.com)

Evidence stage Disclosed volume
Initial requests before tariff approval Approximately 30,000 MW
Requests that paid for formal studies 13,022.7 MW
Binding contracts under the new tariff, as of 12 February 2026 5,642 MW

The utility separately reported 12,219 MW contracted before the tariff, producing 17,861 MW of total contracted projects scheduled progressively through 2035. The older contracts must not be confused with the new-tariff conversion cohort. (aepohio.com)

Desk inference: an enquiry pipeline is a weak substitute for bankable demand. For a developer’s competitive analysis, distinguish requests, paid studies, executed agreements, energised service and accepted IT capacity.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.

  1. www.cbre.com
  2. www.cbre.com
  3. www.cbre.com
  4. www.cbre.com
  5. www.aepohio.com
Read the complete report and source register →