Market data and deal flow · 2026-10-16

Which recent deals and milestones matter to buyers?

The following is a selected transaction register, not an exhaustive market-volume database. Values retain their original economic meaning: enterprise value, financing capacity, projected lease revenue or generation investment.

Event and announcement date Disclosed value and volume Evidenced status and timing Buyer significance
Google–Constellation, 6 October 2026 890 MW of incremental nuclear capacity supported by a 20-year PPA; a separate 2,700 MW, 15-year supply agreement; more than $4.3bn of Constellation investment Announced agreements; first nuclear uprate expected by 2028. Investment is not the disclosed PPA purchase price. (constellationenergy.com) Separate new generation from contracted existing supply. Neither headline establishes service at an unrelated development site.
Applied Digital, Polaris Forge 1, 2 October 2026 Additional 75 MW critical IT load; campus operational total 250 MW Company-reported ready-for-service milestone achieved 1 October 2026, confirmed in results dated 7 October; campus fully leased. (ir.applieddigital.com) A delivered-capacity observation, not a listing of 75 MW available to new customers.
Cipher Digital, Barber Lake, 25 September 2026 Additional approximately $5.2bn contracted revenue; total above $9bn over 20 years Existing Fluidstack lease amended, coupled with a binding subsequent 10-year AI-lab commitment. Hall deliveries expected Q4 2026–Q1 2027. (globenewswire.com) More contracted revenue does not remove change-order or delivery risk.
Vantage, 14 September 2026 $2bn financing facility Closed; five-year revolving platform including extension options, initially collateralised by three development assets; North American scope. (vantage-dc.com) Evidence of development financing—not proof the full amount has been drawn or spent on US construction.
Aligned acquisition, 21 July 2026 Approximately $40bn enterprise value; 51 campuses, more than 6.4 GW operational and planned capacity Acquisition of 100% of equity completed by AIP, MGX and BlackRock’s GIP consortium. Portfolio spans US and Latin American activities. (aligneddc.com) A platform acquisition, not a construction-cost or operating-MW valuation comparable.
TeraWulf–Anthropic, 6 July 2026 Approximately 401 MW critical IT, 20-year lease, approximately $19bn expected contracted revenue Signed lease at Hawesville, Kentucky; capacity delivery expected at signing from late 2027 to early 2028. Rent follows delivery of the relevant premises. (investors.terawulf.com) Useful evidence of long-duration demand, but delivery and credit-support conditions still require diligence.
Applied Digital, Delta Forge 2, 8 June 2026 210 MW critical IT, 15-year take-or-pay lease; approximately $5.2bn base-term revenue Signed with an unnamed US investment-grade hyperscaler; initial operations forecast for Q1 2028 at announcement. Lease reiterated in 7 October 2026 results. (ir.applieddigital.com) Signed future demand, not operating inventory; do not identify the unnamed tenant by inference.

Which deal deserves particular underwriting attention?

Barber Lake is a useful reminder to track amendments, not only initial announcements. Cipher disclosed that it would bear the first $359.3m of costs above the initial budget under the amended arrangement. It also established a reimbursement framework for part of the excess above that amount. Those disclosures sit alongside the increased lease value and revised phasing. (globenewswire.com)

The recommended diligence response is to obtain a change log showing:

  1. Original versus revised delivery milestones.
  2. Additional scope and its technical cause.
  3. Responsibility for cost overruns.
  4. Timing and security of reimbursement.
  5. Rent commencement and customer acceptance by hall.

Why is there no combined deal-flow dollar total?

A combined figure would obscure rather than clarify activity. The register contains a platform enterprise value, a revolving financing commitment, multiyear lease receipts, generation investment and a physical delivery milestone. Adding them would not measure annual spending, annual revenue or newly available capacity.

For the next research pass, maintain separate transaction series:

  • Acquisitions: consideration, enterprise value, acquired stake and completion date.
  • Financing: committed amount, drawn amount, maturity and collateral.
  • Leasing: new critical IT MW, term, commencement and disclosed base-term revenue.
  • Generation: incremental MW versus existing contracted supply.
  • Delivery: accepted IT MW, commissioning milestone and remaining availability.

These are proposed database fields, not additional market estimates.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.

  1. www.constellationenergy.com
  2. ir.applieddigital.com
  3. www.globenewswire.com
  4. vantage-dc.com
  5. aligneddc.com
  6. investors.terawulf.com
  7. ir.applieddigital.com
Read the complete report and source register →