Skip to content
Open buying file ↗
Readiness quiz · 2026-10-16

How should you take the quiz?

Assess one site or facility, one phase and one decision at a time. Do not combine evidence from different parcels, buildings or proposed phases.

Record this decision brief first:

Field Your answer
Site, building and phase
Buyer role and decision owner
Required critical IT MW
Required usable-compute date
Next commitment and payment date
Amount becoming non-refundable or otherwise exposed
Assessment date

Then follow these rules:

  1. Choose one answer per question. A = 0 points; B = 1; C = 2; D = 3.
  2. Score what you can substantiate today. If your position falls between answers, choose the lower one.
  3. Unknown means 0, not “probably fine”. Missing evidence means not established, not necessarily unavailable.
  4. Outsourced does not mean verified. Colocation buyers should request operator evidence or an appropriately scoped independent review; they do not need to own the underlying utility agreement themselves.
  5. Match evidence to the commitment stage. Before land acquisition, an approved design envelope and controlled conditions may be appropriate. Before GPU installation, required physical systems and permissions need to be ready. Before customer activation, acceptance evidence must exist.
  6. Do not award automatic points for “not applicable”. Document why an item is unnecessary and how the underlying requirement is satisfied. For example, a grid-only deployment can score fully on Question 7 without buying bridge generation.

For every answer worth 2 or 3 points, record a document reference, document date, reviewer and unresolved conditions.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.

    Read the complete report and source register →

    Put the evidence to work.

    Keep your requirements, open questions and commitment conditions together.