Yes. The gates are deliberately stronger than the weighted average.
The following is a wholly fictional comparison for an AI operator seeking 10 MW by 31 March 2027. Ratings are assumed evidence-capped inputs, not assessments of real companies.
| Criterion | Operator weight | Offer A rating | Offer B rating |
|---|---|---|---|
| Service entitlement | 18 | 5 | 4 |
| Network delivery | 12 | 5 | 4 |
| Site and permissions | 5 | 0 — NE | 4 |
| Technical compatibility | 18 | 5 | 5 |
| Time to compute | 15 | 3 | 4 |
| Economics | 14 | 5 | 3 |
| Contract protection | 8 | 5 | 4 |
| Acceptance and operations | 6 | 4 | 4 |
| Counterparty capacity | 3 | 4 | 4 |
| Evidence governance | 1 | 4 | 4 |
| Weighted total | 100 | 85.0 | 80.8 |
Offer A: attractive documented technical and commercial terms, but the hypothetical proposed use lacks required permission evidence. G2 is not established. Hold the affected commitment despite 85 points. Its date assessment also remains conditional.
Offer B: all six gates are assumed clear for the specified contracting decision, not for immediate activation. Economics are less attractive but are assumed to remain within the buyer’s approved limits. Offer B is eligible for the next approval step, with subsequent mobilisation and acceptance gates retained.
The example demonstrates the method’s purpose: a five-point category can still contain a condition that stops the whole decision.