Revalidate the project’s applicable process, not merely the date on the last presentation. These are dated developments, not a complete national regulatory update.
| Source development | What it establishes | Scorecard implication |
|---|---|---|
| NERC, 15 October 2026 | Computational-load standards passed final ballot and were to proceed to Board adoption and subsequent regulatory approval—not yet a statement of fully effective US requirements | Ask which existing requirements apply and what emerging requirements could change studies, controls or obligations. (nerc.com) |
| ERCOT, October 2026 materials | The large-load integration page includes Batch Zero verification guidance and distinguishes reference guides from controlling portal RFIs | Obtain the project’s actual classification, outstanding conditions and applicable authorisation; do not treat queue inclusion as energisation approval. (ercot.com) |
| FERC, 18 June 2026 | FERC directed six regional grid operators to justify or reform large-load tariff provisions through tailored proceedings | Check the relevant subsequent filings and effective rules. The June announcement itself does not establish the tariff applicable to an October transaction. (ferc.gov) |
This research did not audit every subsequent regional compliance filing. Project counsel and utility specialists should confirm the rules governing the proposed commitment.
What monitoring cadence should the buyer adopt?
As a proposed desk policy, review critical-path evidence weekly during active delivery, refresh the full scorecard monthly, and reconfirm material facts immediately before each irreversible commitment. Use faster review where circumstances warrant it.
Trigger an immediate reassessment after a change in:
- Capacity allocation, service classification or curtailment conditions.
- Utility milestones, equipment allocation or required approval.
- Rack configuration, cooling design or power envelope.
- Payment commencement, tariff, collateral or funding.
- Contractor, responsible counterparty or acceptance criteria.
- Any assumption supporting the customer activation date.
Preserve the previous assessment. The change memo should state what changed, which gate moved, how the cash or date exposure changed, and who must approve the response.