Scorecard · 2026-10-16

What should go to the investment committee or procurement committee?

Submit a decision sheet backed by an inspectable evidence register—not an unexplained number.

One-page decision sheet

  • [ ] Named supplier, site, phase, workload and commitment.
  • [ ] Utility MW, critical IT MW and buyer allocation shown separately.
  • [ ] Required date and independently assessed dependency schedule.
  • [ ] Six gate statuses, with no blended readiness percentage.
  • [ ] Weighted score, evidence coverage and individual ratings.
  • [ ] Base, delayed and slow-ramp cash requirements.
  • [ ] Upfront, security and contingent obligations separated.
  • [ ] Top unresolved issues, owners, cure dates and hold points.
  • [ ] Technical, energy, legal and commercial reviewer sign-offs.
  • [ ] Specific recommendation: proceed, conditional expenditure, hold or redesign.

Evidence-register fields

Claim ID | criterion/gate | site/phase | supplier assertion | source document and page | issuer | issue/effective date | reviewed date | conditions/expiry | evidence grade | reviewer | unresolved question | next confirmation

Restrict confidential utility, financial and engineering documents to authorised reviewers. Disclose referral remuneration and supplier funding; neither should purchase a higher rating.

Bottom line: use the weighted score to compare documented advantages. Use the gates to decide whether those advantages are relevant to the next commitment. The winning offer is the one whose evidence supports the buyer’s actual load, date and obligations.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.