Assess six gates separately. Never publish their average as a readiness percentage.
The table is a proposed evidence checklist, not a national permitting pathway.
| Gate | Evidence to request | What a satisfactory position looks like | What should stop or condition the commitment |
|---|---|---|---|
| G1. Land and access | Title/lease/option documents; permitted use; access, utility and fibre easements; relevant assignments | Rights cover the intended phase, delivery routes and commitment period | Expiring control, missing rights or a proposed assignment that has not been accepted |
| G2. Planning and permits | Jurisdiction-specific permission register; approval documents; conditions; appeal status; water, air, noise and fire requirements where applicable | Required permissions for the next activity are established; later approvals have identified owners and credible paths | A required approval is refused, incompatible with the design, or unsupported at the commitment stage |
| G3. Utility arrangements | Site-specific correspondence, studies, agreements, delivery point, capacity schedule, service conditions and payment requirements | The buyer can distinguish requested, studied, contracted and energised capacity | A marketing claim, preliminary letter or supply contract is being substituted for the required service evidence |
| G4. Network works | Utility/network scope; dependencies; rights of way; funding; procurement; construction and energisation milestones | Every material upstream work package has a responsible party, evidenced status and dated dependency | Unresolved transmission works, equipment allocation or approval assumptions underpin the promised date |
| G5. Equipment and facility systems | Electrical and cooling design; equipment orders; allocation records; water and fibre arrangements; interface matrix | The specified racks can be supported at the required density and resilience, with delivery responsibilities assigned | Unsupported “liquid-ready” claims, unavailable components or an unowned integration task |
| G6. Commissioning and acceptance | Test strategy, scripts, resource bookings, witness rights, acceptance criteria and eventual results | The next-stage commitment is supported by an executable acceptance plan; activation is supported by completed tests | Energisation or building completion is being treated as proof of usable compute |
Assign one of four statuses to each gate:
- Clear for this decision: evidence meets the requirement for the specific release of money or equipment.
- Conditional: a defined cure remains; specify its owner, deadline, cost and contractual hold point.
- Blocked: evidence identifies an incompatibility or dependency that defeats the requirement without a material change.
- Not established: evidence is missing, stale or contradictory. This means insufficient proof—not necessarily unavailable capacity.
How should the gates change with project stage?
A development plan should not fail merely because it has not yet been built. Equally, a construction plan cannot substantiate a claim that capacity is ready to operate.
| Commitment stage | Recommended gate standard |
|---|---|
| Bounded feasibility or option expenditure | Identified uncertainties, access to investigate them, capped exposure and a credible route to resolve them |
| Irreversible land, utility, construction or lease commitment | Stage-relevant rights and agreements established; future conditions explicitly allocated, funded and protected by hold points or accepted risk limits |
| Hardware mobilisation or operational activation | Required physical capacity, permissions, integration and tests completed for that release; documented acceptance of any limited residual items |
A future commissioning plan may therefore be satisfactory for a construction decision, but it is not a substitute for commissioning results at activation.
Additional vetoes: failure to meet a mandatory capacity, deadline, resilience, security or funding constraint overrides the total score. Put buyer-specific non-negotiables on the cover sheet before scoring.
Sources & research context
Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.