Which conditions must pass before the weighted score matters?

Assess six gates separately. Never publish their average as a readiness percentage.

The table is a proposed evidence checklist, not a national permitting pathway.

Gate Evidence to request What a satisfactory position looks like What should stop or condition the commitment
G1. Land and access Title/lease/option documents; permitted use; access, utility and fibre easements; relevant assignments Rights cover the intended phase, delivery routes and commitment period Expiring control, missing rights or a proposed assignment that has not been accepted
G2. Planning and permits Jurisdiction-specific permission register; approval documents; conditions; appeal status; water, air, noise and fire requirements where applicable Required permissions for the next activity are established; later approvals have identified owners and credible paths A required approval is refused, incompatible with the design, or unsupported at the commitment stage
G3. Utility arrangements Site-specific correspondence, studies, agreements, delivery point, capacity schedule, service conditions and payment requirements The buyer can distinguish requested, studied, contracted and energised capacity A marketing claim, preliminary letter or supply contract is being substituted for the required service evidence
G4. Network works Utility/network scope; dependencies; rights of way; funding; procurement; construction and energisation milestones Every material upstream work package has a responsible party, evidenced status and dated dependency Unresolved transmission works, equipment allocation or approval assumptions underpin the promised date
G5. Equipment and facility systems Electrical and cooling design; equipment orders; allocation records; water and fibre arrangements; interface matrix The specified racks can be supported at the required density and resilience, with delivery responsibilities assigned Unsupported “liquid-ready” claims, unavailable components or an unowned integration task
G6. Commissioning and acceptance Test strategy, scripts, resource bookings, witness rights, acceptance criteria and eventual results The next-stage commitment is supported by an executable acceptance plan; activation is supported by completed tests Energisation or building completion is being treated as proof of usable compute

Assign one of four statuses to each gate:

  • Clear for this decision: evidence meets the requirement for the specific release of money or equipment.
  • Conditional: a defined cure remains; specify its owner, deadline, cost and contractual hold point.
  • Blocked: evidence identifies an incompatibility or dependency that defeats the requirement without a material change.
  • Not established: evidence is missing, stale or contradictory. This means insufficient proof—not necessarily unavailable capacity.

How should the gates change with project stage?

A development plan should not fail merely because it has not yet been built. Equally, a construction plan cannot substantiate a claim that capacity is ready to operate.

Commitment stage Recommended gate standard
Bounded feasibility or option expenditure Identified uncertainties, access to investigate them, capped exposure and a credible route to resolve them
Irreversible land, utility, construction or lease commitment Stage-relevant rights and agreements established; future conditions explicitly allocated, funded and protected by hold points or accepted risk limits
Hardware mobilisation or operational activation Required physical capacity, permissions, integration and tests completed for that release; documented acceptance of any limited residual items

A future commissioning plan may therefore be satisfactory for a construction decision, but it is not a substitute for commissioning results at activation.

Additional vetoes: failure to meet a mandatory capacity, deadline, resilience, security or funding constraint overrides the total score. Put buyer-specific non-negotiables on the cover sheet before scoring.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.