Scorecard · 2026-10-16

What weights should buyers use?

Use the development profile for site and build decisions; use the AI operator profile for near-term high-density colocation procurement. Both total 100 points.

Criterion Developer weight AI operator weight Primary accountable reviewer
1. Utility service and capacity entitlement 20 18 Energy lead and counsel
2. Network works and energisation deliverability 16 12 Utility interface lead and electrical engineer
3. Land, permissions and site constraints 12 5 Development lead and local specialists
4. Electrical, cooling and connectivity compatibility 10 18 Infrastructure engineering lead
5. Equipment delivery and time to compute 12 15 Integrated programme owner
6. Full costs and ramp economics 14 14 Energy procurement and finance
7. Contractual allocation of delivery risk 7 8 Commercial lead and counsel
8. Commissioning and operational readiness 5 6 Commissioning authority and operations
9. Counterparty execution and financial capacity 3 3 Procurement and finance
10. Evidence governance and change control 1 1 Diligence owner
Total 100 100

These weights reflect the desk’s proposed priorities, not measured failure frequencies. Commissioning and permissions remain mandatory gates even where their comparative weight is modest.

Freeze weights before evaluating offers. If the buyer changes the brief, rescore every option. Do not remove difficult criteria or redistribute missing-evidence weights to improve an option’s total.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.

    Read the complete report and source register →

    Put the evidence to work.

    Keep your requirements, open questions and commitment conditions together.