Use the development profile for site and build decisions; use the AI operator profile for near-term high-density colocation procurement. Both total 100 points.
| Criterion | Developer weight | AI operator weight | Primary accountable reviewer |
|---|---|---|---|
| 1. Utility service and capacity entitlement | 20 | 18 | Energy lead and counsel |
| 2. Network works and energisation deliverability | 16 | 12 | Utility interface lead and electrical engineer |
| 3. Land, permissions and site constraints | 12 | 5 | Development lead and local specialists |
| 4. Electrical, cooling and connectivity compatibility | 10 | 18 | Infrastructure engineering lead |
| 5. Equipment delivery and time to compute | 12 | 15 | Integrated programme owner |
| 6. Full costs and ramp economics | 14 | 14 | Energy procurement and finance |
| 7. Contractual allocation of delivery risk | 7 | 8 | Commercial lead and counsel |
| 8. Commissioning and operational readiness | 5 | 6 | Commissioning authority and operations |
| 9. Counterparty execution and financial capacity | 3 | 3 | Procurement and finance |
| 10. Evidence governance and change control | 1 | 1 | Diligence owner |
| Total | 100 | 100 |
These weights reflect the desk’s proposed priorities, not measured failure frequencies. Commissioning and permissions remain mandatory gates even where their comparative weight is modest.
Freeze weights before evaluating offers. If the buyer changes the brief, rescore every option. Do not remove difficult criteria or redistribute missing-evidence weights to improve an option’s total.
Sources & research context
Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.