The following anchors are desk-designed scoring rules. Apply them at the project’s actual stage.
| Criterion | Weak: 0–1 | Adequate: 3 | Strong: 5 | Minimum evidence pack |
|---|---|---|---|---|
| 1. Service and entitlement | “Power secured” without the relevant service terms; requested and allocated MW confused | Site and phase identified; service scope documented; remaining conditions explicit | Applicable rights, capacity allocations and operating restrictions independently reconciled; no material entitlement ambiguity | Agreements, studies, load schedule, delivery-point diagram, allocation register |
| 2. Network delivery | Date depends on unspecified upstream work or generic equipment lead times | Network scope, owners and milestone dependencies identified; some contingencies remain | Critical work status confirmed with responsible parties; procurement, rights and approvals evidenced; delay response evaluated | Utility schedule, work packages, approvals, order acknowledgements, progress evidence |
| 3. Site and permissions | Land rights, intended use or a required permission unsupported | Site-specific diligence complete enough to identify approval conditions and mitigation costs | Stage-required rights and permissions confirmed; environmental, water and physical constraints independently challenged | Rights schedule, permit register, specialist reports, authority correspondence |
| 4. Technical compatibility | Campus-average density or “liquid-ready” label substitutes for rack-level proof | Engineering design matches the proposed systems, with documented interface exceptions | End-to-end compatibility validated at required load and operating conditions, including degraded modes where required | Single-lines, rack layout, cooling calculations, interface specifications, network design |
| 5. Time to compute | Delivery date ends at shell completion or energisation | Integrated dependency schedule includes fit-out, fibre, installation and acceptance | Critical path and resource allocations independently challenged; float, recovery options and late-delivery scenarios evidenced | Logic-linked schedule, equipment allocations, installer commitments, responsibility matrix |
| 6. Costs and ramp | Energy-only rate presented as the full bill; deposits and minimums omitted | Monthly base and downside cases include material tariff and contractual obligations | Billing logic independently reconciled; slower ramp, delay, curtailment and exit exposures remain within buyer limits | Applicable tariff/riders, contract schedules, model, sample bill or utility calculation |
| 7. Contract protection | Payment commencement is detached from acceptance; interface failures have no owner | Scope, milestones, exclusions and remedies documented, with recognised negotiation gaps | Obligations align across contracts; acceptance, change control, security and remedies are executable and commercially acceptable | Draft/final contracts, scope matrix, guarantee/security documents, counsel issues list |
| 8. Acceptance and operations | Certificate, brand or equipment startup substituted for integrated acceptance | Stage-appropriate test plan, staffing and handover scope agreed | Relevant acceptance evidence and operational capability independently verified; critical defects closed or explicitly controlled | Test scripts/results, defect log, operating procedures, training and maintenance records |
| 9. Counterparty capacity | Project depends on uncommitted funding, unnamed subcontractors or unverifiable references | Delivery team, funding route and relevant references identified | Project-specific resources and funding substantiated; comparable delivery references checked; substitution/failure plan evaluated | Financial evidence, project funding, organisation chart, subcontractor and reference checks |
| 10. Evidence governance | Dates conflict; no version owner; material changes disclosed informally | Controlled document register and regular updates | Traceable changes automatically trigger reassessment of affected gates, costs and dates | Evidence register, decision log, notification obligations, conflict disclosures |
Where should overlapping risks be scored?
Keep the assessment boundaries explicit:
- Criterion 1 scores service rights and conditions; criterion 2 scores physical network delivery.
- Criterion 4 scores technical capability; criterion 5 scores delivery sequencing; criterion 8 scores acceptance and operation.
- Criterion 6 scores economic exposure; criterion 7 scores who contractually bears it.
- Criterion 10 scores the change-control process, not a second generic penalty for documents already capped elsewhere.
One event can affect several outcomes, but the economic model must not count the same cash exposure twice.
Sources & research context
Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.