What do good and bad look like for each criterion?

The following anchors are desk-designed scoring rules. Apply them at the project’s actual stage.

Criterion Weak: 0–1 Adequate: 3 Strong: 5 Minimum evidence pack
1. Service and entitlement “Power secured” without the relevant service terms; requested and allocated MW confused Site and phase identified; service scope documented; remaining conditions explicit Applicable rights, capacity allocations and operating restrictions independently reconciled; no material entitlement ambiguity Agreements, studies, load schedule, delivery-point diagram, allocation register
2. Network delivery Date depends on unspecified upstream work or generic equipment lead times Network scope, owners and milestone dependencies identified; some contingencies remain Critical work status confirmed with responsible parties; procurement, rights and approvals evidenced; delay response evaluated Utility schedule, work packages, approvals, order acknowledgements, progress evidence
3. Site and permissions Land rights, intended use or a required permission unsupported Site-specific diligence complete enough to identify approval conditions and mitigation costs Stage-required rights and permissions confirmed; environmental, water and physical constraints independently challenged Rights schedule, permit register, specialist reports, authority correspondence
4. Technical compatibility Campus-average density or “liquid-ready” label substitutes for rack-level proof Engineering design matches the proposed systems, with documented interface exceptions End-to-end compatibility validated at required load and operating conditions, including degraded modes where required Single-lines, rack layout, cooling calculations, interface specifications, network design
5. Time to compute Delivery date ends at shell completion or energisation Integrated dependency schedule includes fit-out, fibre, installation and acceptance Critical path and resource allocations independently challenged; float, recovery options and late-delivery scenarios evidenced Logic-linked schedule, equipment allocations, installer commitments, responsibility matrix
6. Costs and ramp Energy-only rate presented as the full bill; deposits and minimums omitted Monthly base and downside cases include material tariff and contractual obligations Billing logic independently reconciled; slower ramp, delay, curtailment and exit exposures remain within buyer limits Applicable tariff/riders, contract schedules, model, sample bill or utility calculation
7. Contract protection Payment commencement is detached from acceptance; interface failures have no owner Scope, milestones, exclusions and remedies documented, with recognised negotiation gaps Obligations align across contracts; acceptance, change control, security and remedies are executable and commercially acceptable Draft/final contracts, scope matrix, guarantee/security documents, counsel issues list
8. Acceptance and operations Certificate, brand or equipment startup substituted for integrated acceptance Stage-appropriate test plan, staffing and handover scope agreed Relevant acceptance evidence and operational capability independently verified; critical defects closed or explicitly controlled Test scripts/results, defect log, operating procedures, training and maintenance records
9. Counterparty capacity Project depends on uncommitted funding, unnamed subcontractors or unverifiable references Delivery team, funding route and relevant references identified Project-specific resources and funding substantiated; comparable delivery references checked; substitution/failure plan evaluated Financial evidence, project funding, organisation chart, subcontractor and reference checks
10. Evidence governance Dates conflict; no version owner; material changes disclosed informally Controlled document register and regular updates Traceable changes automatically trigger reassessment of affected gates, costs and dates Evidence register, decision log, notification obligations, conflict disclosures

Where should overlapping risks be scored?

Keep the assessment boundaries explicit:

  • Criterion 1 scores service rights and conditions; criterion 2 scores physical network delivery.
  • Criterion 4 scores technical capability; criterion 5 scores delivery sequencing; criterion 8 scores acceptance and operation.
  • Criterion 6 scores economic exposure; criterion 7 scores who contractually bears it.
  • Criterion 10 scores the change-control process, not a second generic penalty for documents already capped elsewhere.

One event can affect several outcomes, but the economic model must not count the same cash exposure twice.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.