Trace the claim from the named delivery point to the named phase, then identify every condition between that evidence and operation.
Dominion’s public data-centre process separates preliminary site evaluation from infrastructure design, rights of way, permitting, material procurement, regulatory filings and construction. Its site-selection assistance can include a will-serve letter. This supports treating that letter as one document in a delivery chain—not as a universal statement that all later dependencies are complete. (dominionenergy.com)
Ask the supplier and serving utility:
- Which legal entity holds the service rights, and can the proposed buyer rely on or receive those rights?
- What is requested, studied, contracted, currently energised and already allocated elsewhere?
- Which date is an estimate, which is a contractual milestone, and what conditions qualify each?
- Which upstream works remain, who funds them, and what evidence supports their dates?
- What operating limits apply: import cap, curtailment, ramp limits, backup arrangements or phased service?
- What changes to hardware, load behaviour or phase size require renewed review?
NERC’s July 2025 large-load white paper identifies issues including load behaviour, ride-through, power quality, stability and observability. The buyer implication is to request the load model and operating assumptions used for the project’s studies, rather than relying solely on a static MW figure. (nerc.com)
Does a PPA establish physical service?
Not by itself. EPA distinguishes physical PPAs, which involve electricity delivery, from financial PPAs, which do not. This scorecard therefore evaluates energy procurement separately from evidence that the specific site, connection and facilities can support the buyer’s load. (epa.gov)
Do not score a credible PPA as worthless. Score it for what it establishes—then request the separate delivery evidence.
Does bridge power remove the grid dependency?
Treat it as an additional delivery plan, not an automatic cure. Require a separate review of fuel, equipment, operating permissions, emissions, maintenance, redundancy, grid interaction and transition to permanent service.
EPA’s data-centre resources distinguish applicable stationary-engine requirements and specific emergency-operation treatment. Do not assume permissions for emergency backup generation authorise the proposed routine bridge-power duty. Obtain a project-specific determination from the relevant environmental specialists and permitting authority. (epa.gov)