How should full electricity and colocation costs be scored?

Score the monthly payment obligation under the buyer’s ramp—not the advertised cents per kWh. Berkeley Lab’s August 2026 research examines large-load tariff structures and service agreements as mechanisms for managing operational and financial risks, including underutilised investment. It provides context, not a substitute for the tariff and contract applicable to a particular site. (eta.lbl.gov)

Build four separate schedules

Schedule Include Avoid
Recurring operating charges Capacity rent, energy, applicable demand charges, riders, taxes, support and connectivity Adding utility costs again when already included in the operator’s price
One-off expenditure Fit-out, connection contributions, integration, testing and mobilisation Treating a non-refundable contribution as recoverable security
Liquidity and security Deposits, collateral, letters of credit, release conditions and financing costs Treating posted collateral principal as an ordinary operating expense
Contingent liabilities Exit obligations, delay payments, unamortised infrastructure and restoration costs Assuming every contingency is both certain and immediately payable

For an all-grid-supplied model with consistent measurement boundaries:

IT energy, MWh = average IT MW × hours in the month

Facility energy, MWh = IT energy × modelled monthly PUE

Use separate energy balances where on-site generation, storage, exports or shared meters apply. Do not derive billing peak demand from monthly energy consumption.

Construct each bill from its actual charging rules. Different demand components may use different measured peaks, ratchets or contract floors; minimum-charge provisions must be applied to the appropriate components rather than stacked indiscriminately.

What does an actual minimum-demand provision illustrate?

AEP Ohio’s public DCT summary describes a contract-capacity minimum and an 11-month billing-demand ratchet. For the 25,001–75,000 kW band, the stated contract-capacity floor is 15,000 kW plus 85% of capacity above 25,000 kW. A 50,000 kW assumption therefore produces 36,250 kW before considering other applicable billing provisions. This is not a claim that every data centre pays for 85% of its contracted energy. (aepohio.com)

That calculation illustrates the published summary, not a customer bill. Confirm applicability, aggregation, ramp provisions, current tariff sheets and negotiated terms with the utility and the buyer’s energy adviser.

Which scenarios are mandatory in this methodology?

Model at least:

  • The buyer’s expected commissioning and utilisation ramp.
  • Later activation with original payment commencement dates.
  • Slower utilisation after activation.
  • A smaller first phase with unchanged minimum commitments.
  • Applicable curtailment or import restrictions.
  • Exit or cancellation at the next major decision point.

Report recurring cost per reserved IT kW-month, electricity cost per metered MWh, total monthly cash requirements and the maximum contingent exposure. If IT consumption is zero, report the consumption-based unit metric as not meaningful—not as zero cost.

How should delay exposure be presented?

Separate cash paid before production from incremental cost and deferred contribution.

Illustration only: reserving 10,000 kW at an assumed $150/kW-month for six months before productive use creates $9 million of pre-productive capacity rent if billing continues throughout. This is not automatically $9 million of incremental lifetime loss; the answer depends on commencement, term extension, recovery and utilisation assumptions.

Show hardware storage, financing, duplicate facilities and customer remedies separately. Model deferred contribution using buyer-confirmed margins and recovery assumptions. Do not add all delayed revenue to cash costs as though every delayed sale were permanently lost.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.

  1. eta.lbl.gov
  2. www.aepohio.com
Read the complete report and source register →