Scorecard · 2026-10-16

What evidence makes a facility genuinely liquid-ready?

Require a configuration-specific compatibility matrix, not a cooling label. NVIDIA’s DGX GB200 SuperPOD architecture explicitly combines liquid and air cooling. A facility assessment for that configuration must therefore address both heat-removal paths. This example should not be generalised into specifications for every AI rack. (docs.nvidia.com)

Use the following proposed procurement matrix:

Interface Buyer evidence requirement
Electrical supply Approved rack power envelope, feeds, protection, connectors, distribution and required failure-mode capability
Liquid circuit Manufacturer-approved coolant, supply/return conditions, flow, pressure, materials, filtration and connection interfaces
Heat rejection Capacity at the relevant design conditions, shared loads and required maintenance/degraded modes
Residual air cooling Non-liquid-cooled rack components, network equipment and other room loads
Controls Leak detection, isolation, alarm routing, shutdown responsibility and IT/operational-technology integration
Physical deployment Filled rack weight, structural review, handling route, clearances, hoses, cable paths and maintenance access
Commercial boundary Who supplies, installs, cleans, fills, tests, operates and warrants each interface

NVIDIA’s Mission Control documentation assigns different leak-detection functions across trays, racks and facility systems and identifies customer-provided building-management-system requirements. This is a concrete reason to make controls ownership part of procurement rather than leaving it to post-delivery integration. (docs.nvidia.com)

OCP’s pre-commissioning guidance addresses technology-cooling-system pipework cleaning, hydrotesting, flushing and preparation. Its stated scope does not include commissioning the CDUs and racks themselves. Request both the pipework preparation records and the additional equipment/system acceptance evidence. (opencompute.org)

Scoring rule: an unresolved interface capable of preventing the intended deployment holds G5. Strong evidence elsewhere in the cooling design cannot compensate for it.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.

  1. docs.nvidia.com
  2. docs.nvidia.com
  3. www.opencompute.org