How should time to compute and acceptance be tested?

Build the schedule backwards from customer-usable compute, then verify every predecessor and hand-off.

Use an integrated sequence covering:

  1. Utility/network readiness and required permissions.
  2. Facility electrical, cooling and controls completion.
  3. Fibre and external connectivity readiness.
  4. Equipment delivery, handling and installation.
  5. Facility-system testing and defect closure.
  6. Rack, network and software integration.
  7. Workload-specific acceptance and operational handover.

Do not simply add every task duration: some activities can run in parallel, while others cannot. For each activity, record its predecessors, duration basis, owner, evidence, resources, float and recovery option. Unknown durations remain unknown or explicitly scenario-based.

What belongs in acceptance criteria?

The desk recommends buyer-approved criteria for the required load, thermal conditions, interfaces, failover behaviour, alarms, connectivity, defect closure and handover documentation. Technical specialists should define safe procedures and pass/fail values for the actual design.

Uptime distinguishes design-document certification from constructed-facility certification; the latter includes live demonstrations of the installed facility. Its award terms also identify the particular phase or facility scope covered. Verify the certificate’s scope and status rather than treating a campus-level badge as acceptance of the buyer’s deployment. (uptimeinstitute.com)

As a primary-source procurement signal, Anthropic’s published power-and-cooling quality role includes supplier qualification, inspection/test plans, factory acceptance tests and documentation expectations embedded in RFPs and contracts. A job posting establishes those stated responsibilities—not the performance of any particular project or supplier. (job-boards.greenhouse.io)

Recommended contract question: what exact acceptance event starts each payment, and which buyer-caused or supplier-caused exceptions alter that event? Have counsel reconcile this across the facility, hardware, utility and integration agreements.

Sources & research context

Research snapshot: 2026-10-16. Sources and limitations are retained as supplied.